Hammer crusher installation commissioning

1, the installation can be selected according to sources of raw materials terrain.
2, the machine by the anchor bolts in the concrete , the design of the foundation when leaving a row of mine shafts , and its slope can not be less than 50 °, but the user can also be based feeder and transport equipment custom .
3, the motor should be installed with the inlet in the opposite direction .
4 , easy to use electrical Grain testing equipment in order to better position .
5 , before commissioning should first check the fasteners are completely secure.
6, check whether the body falls unbreakable metal or other debris .
7, check whether the proper bearing lubrication .
8 , turn the rotor by hand to see if they are functioning properly , without friction phenomenon , if recognized as unimpeded movement when empty before starting, test after half an hour no noise, no swing , bearing temperature does not exceed 30 ℃, can be load test .